WA Smart Services Group completed the commissioning of a newly constructed camp expansion at the Wiluna remote mine site, ensuring all electrical systems were fully operational, compliant, and ready for occupancy. The project involved comprehensive testing, verification, and coordination to support a seamless handover and ongoing site operations.
Mining & Industrial
Wiluna Mine Site Camp Expansion Commissioning
Wiluna Region
Commissioning Critical Infrastructure For Remote Mining Operations

Client Background
The Wiluna mine site required the commissioning of a newly developed camp expansion designed to support workforce accommodation and site operations. Given the remote location and demanding operating environment, it was essential that all electrical infrastructure was thoroughly tested, verified, and compliant prior to occupancy. Reliability, safety, and adherence to mining standards were critical to ensuring the facility could support day-to-day operations without disruption.
Scope of Work
WA Smart Services Group was engaged to undertake the commissioning of the camp's electrical infrastructure. Works included detailed inspections, testing, and verification of power distribution systems, lighting installations, switchboards, circuits, and associated electrical equipment. Functional testing was completed under operational conditions to confirm performance, while all systems were reviewed to ensure compliance with relevant mining regulations and AS/NZS standards.
Key Outcomes
The commissioning process was completed efficiently and in line with project timelines, supporting a smooth transition from construction to operation. Working closely with site management and project stakeholders, our team identified and resolved defects prior to handover, ensuring all systems operated as intended. The completed camp expansion now provides reliable electrical services to support workforce accommodation and ongoing mining operations in a demanding remote environment.

Project Highlights
Commissioned a newly constructed camp expansion at the Wiluna mine site
Completed testing and verification of power distribution, lighting, and electrical infrastructure
Ensured compliance with mining regulations and AS/NZS standards
Identified and resolved defects prior to occupancy and handover
Delivered a safe, efficient commissioning process within project timeframes